I was given a deadline a few days ago to have the kitchen cabinets set so that my countertops could be measured on April 22nd. Sometimes a deadline is what you need to kick it in gear and sometimes it just causes stress and in our case it's little of both. Before we can set the cabinets the new floors have to be installed, stained and protected. Before the floors can be done the painting needs to be at least primed. So that's what we've been doing. The walls, ceilings and trim have all been primed and the ceilings all painted.
We have now started installing the 3/4" oak in the third bedroom and kitchen. The rest of the hardwood is in good shape it just needs to be sanded and refinished.